Online Exclusive: Bridge to Time Savings
Online-only Articles -
Online-only 2009
Innovative construction techniques and high-tech surveying
equipment kept a project to build a bridge near Dallas, Texas on a fast track.
Now complete, it drastically cuts driving time.
By Don Talend
Lewisville Lake, a 23,280-acre lake just northwest of Dallas,
Texas, is a favorite of area sailboaters and fishermen, but in recent years, it
hasn’t done much for drivers. Two major north-south arterials that stretch
north of Dallas, I-35E and the Dallas North Tollway, straddle the lake and, previously,
no east-west connecting route existed between the two. Circumventing the lake
to get from one arterial to the other took drivers half an hour or more.
Part of the solution to this problem is the 2.03-mile-long
Lewisville Lake Toll Bridge, which opened to vehicular traffic in August. Combine
a high-profile bridge project, a fast-track schedule, and a big lake, and the
contractor needs the most high-tech tools it can find to survey the structure
with pinpoint accuracy amid strong wave action.
The North Texas Tollway Authority (NTTA) awarded Des Moines,
Iowa-based Jensen Construction Company a $93 million contract to erect a bridge
over the lake. The company began work on a 1,000-foot-long flow-easement bridge
on the west side of the lake in late 2006 and then started constructing the
lake bridge in February 2007. This contract forms the centerpiece of roughly
$220 million in congestion-easing road improvements to be made to a surrounding
13.7-mile corridor.
The center of the bridge has a tied arch span that supports the
bridge deck with cable hangers. This segment also features a 370-foot-long
center span with the bents, i.e., piers, spaced to allow plenty of room for
boat traffic to pass under the bridge. Two arch bents supporting the center span,
combined with an arched steel truss structure, give the structure a distinctive
architectural appearance, as the arch bents themselves resemble sails. Adding
to the nautical appearance of the structure will be four more pairs of light
bents, which resemble lighthouses and shine light to the north and south of the
bridge.
The majority of the spans are designed to use prestressed concrete
beams, which have a typical length of 120 feet. Bexar Concrete, San Antonio, precasted the
beams, deck panels, and skirt panels and trucked them to the jobsite. At a dock
in Lake Dallas on the west side of the lake, the precast elements were unloaded
onto barges, shipped, and erected.

The timeframe on Jensen Construction’s contract was only 30 months,
meaning productivity was king. Ryan Cheeseman, P.E., project engineer for
Jensen, fully recognized that time is money on this project. “It’s the most
work in the least amount of time we’ve done,” he notes. As a result of the
tight schedule, Jensen Construction used equipment and practices that increased
construction efficiency as much as possible while adhering to design
tolerances. Two examples are the use of special light bent and arch bent
footing forms that also work as temporary cofferdams and GNSS (Global
Navigation Satellite System) receivers for surveying most of the bridge
substructure and superstructure.
Forms
Double as Cofferdams
The most unique design and construction aspects of the Lewisville
Lake Toll Bridge are the arch bents, light bents, and the footings supporting these
bridge bents. These bent footing forms are also temporary cofferdams. While
conventional cofferdams are constructed by driving sheetpiling into the bed of
a body of water, building a seal around the base of the sheetpiling and pumping
out the enclosure, the footings on this project replaced the sheet piling with
a concrete footing cast above the surface. “Conventional cofferdams are very
tedious and time-consuming, and they cost a lot of money,” Cheeseman explains.
“With this type of footing, we could complete that whole footing in about a
week and half, which kept things moving really quickly. It’s just like a
temporary cofferdam using the formwork of the footing as the cofferdam.”
Drill shaft casings—60, 72, 84, or 96 inches in diameter—were
driven into the lake bed by ATS Drilling, Fort Worth, Texas. A one-foot-thick
footing bottom slab was cast on a barge, and the footing forms were set on the
bottom slab. The
forms and slab are then set on top of the drilled shafts and supported by steel
hangers welded to the drilled shaft casing. Workers pump out water, install the
rebar, and place concrete for the footing. Divers strip the footing, and skirt
panels are hung on the sides of the footing. Finally, a footing cap is placed to
get the footing to grade.
The arch bents are hollow and have a thickness of 2.5 feet. Each bent
required five concrete placements prior to construction of the bent caps. A
vertical section facing the center of the lake was cast. Then a sloped section
facing the shoreline was formed and cast. At the top of these two sections, a
slab was cast that forms the floor of utility rooms. Another vertical section
that forms the utility room walls was cast on top of the slab, and the fifth
placement was the roof of the utility rooms. The caps were then constructed on
top of the bents and support the beam seats. All columns and caps on the project were
mass concrete placements and required temperature-controlled concrete. The
concrete supplier, Dallas-based TXI, used liquid nitrogen in the batching
concrete to reduce the heat of hydration in the cement paste, one of the most
extreme measures available for reducing concrete temperature in massive
concrete structures. Temperature-monitoring devices were also used to check
core temperatures versus external temperatures and safeguard against structural
cracking.
Surveying
Tools Improve Productivity
Jensen Construction used Topcon HiPer Lite+ GNSS receivers to
survey the bridge substructure all the way up to the beam seats. Cheeseman
points out that GNSS was used where possible to address productivity and
logistical issues. A Topcon GTS-235W total station was used for profiling each
of the girders for setting the decking, and on the superstructure, the total
station was used for deck and paving grades. In these areas, he explains,
pinpoint accuracy was essential. The GNSS equipment was normally accurate to
within about five-eighths of an inch of target on a typical day, Cheeseman
reports.
In recent years, surveyors have begun to rely on GNSS equipment
for more and more topographical surveying work once control is defined on a
worksite, with a stationary base and mobile rover working together to provide accurate
topographical data. Recently, these systems have become even more reliable and
accurate as they have added compatibility with the Russian GLONASS satellite
constellation to the GPS satellite constellation. This dual-constellation
capability roughly doubles the number of signals available to the GNSS
antenna/receivers and provides a high degree of positioning accuracy.
Working on water with strong winds and currents makes the use of
GNSS surveying equipment a beneficial option where feasible, Cheeseman says. A
professional surveying firm was first brought in to define control, and as the first
footings and bents were constructed, Cheeseman and Jensen’s surveying team had
several “crow’s nests” constructed along the shoreline. These used 24-inch pipe
pile-driven into the lakebed and small iron work platforms welded to the top of
the pipe. But the wave action on the lake caused slight movement of the crow’s
nests and compromised surveying accuracy.
“We used the crow’s nests just enough to get the control traversed
from one side to the other and got coordinates defined, and from that point, we
abandoned them because they weren’t doing us any good,” says Cheeseman. “They
moved so much with the wave action that we couldn’t set up an instrument and be
confident that every day we were going to repeat our locations.”

Cheeseman, along with Jensen Construction surveyors Laine Buller
and Marcus Marion, had already spearheaded efforts to start incorporating the
use of GNSS surveying equipment in the company’s bridge work. Buller, who has
been a surveyor for about 10 years, joined Jensen Construction for her second
stint at the start of the Lewisville Lake bridge project. Before work began on
the project, Jensen Construction purchased the HiPer Lite+ unit from Griner
& Schmitz, a distributor of surveying and construction equipment in Kansas
City. “From a productivity and constructability standpoint, we went to the GNSS
knowing we could get to within a tenth of a foot or better every day, so we
just ran with it,” Cheeseman reveals.
The total station maintained its place where ultra-pinpoint
accuracy was necessary on this project, but the location of the GNSS receiver
is less dependent on a level, stable surface than the total station, so Jensen
Construction’s surveying crew could spend more time surveying from a wider
range of locations without devoting as much time to equipment setup. Signal
reliability was not much of an issue on this project, Cheeseman adds. Noting
that the receiver gets signals from the base station located on high ground all
the way to the other side of the lake—a distance of about 10,000 feet—he points
out that signal loss is rare.
The technology was admittedly a bit intimidating at first in that
the crew double-checked the accuracy of readings with the total station. As the
total station verified the accuracy of the GNSS equipment, the confidence grew.
Buller notes that she checks two control points every morning to ensure an
accurate reference. “We go out on the lake and then when we come back, we check
the point as we get on land every time just to make sure it didn’t get switched
around,” she adds.

The leap in productivity gained from using the GNSS equipment
proved noticeably significant, Buller says. “I think it would have taken two
other surveyors” to maintain the level of productivity that Jensen Construction
enjoyed without the use of the equipment. “We love this GNSS because you carry
it out there, and there’s no setting it up and going back to shoot your
backsight. It’s excellent, especially on this water.”
Buller notes that time truly is money on a project with a
fast-track schedule such as this. “It cuts your survey cost in half. You’re
always looking for places to cut costs. You have your initial cost of buying
the GNSS equipment, but your labor is cut in half after that.”
Now complete, the structure can handle 25,000 cars a day and
drastically reduces commute times for many. The NTTA estimates that the bridge
reduces driving time from Lake Dallas, the location of the overflow bridge on
the lake’s west side, to Little Elm on the east side from 45 to 10 minutes.
Thanks to innovation and technology, the Lewisville Lake Toll Bridge itself has
joined drivers on a fast track.
Don Talend of Write Results in West Dundee, IL is a publicity and
communications project manager specializing in the construction industry.
» Back to our Online-only 2009 Issue